Science Building renovations

Science Building renderingIn June 2012, Michigan Gov. Rick Snyder approved a $30 million capital outlay that will help UM-Dearborn fund its Science Building renovation project. Keep up to date with the progress of the project.

Headlines:
First phase of Science Building renovations completed (April 6, 2015)
Regents approve schematic designs for Science Building renovations (April 19, 2013)
University receives $30 million capital outlay to renovate Science Building (July 16, 2012)

Construction timeline:

  • Spring 2015 (Phase II): Renovations and additions begin in the Science Building; Renovations and additions complete by Fall 2016
  • Spring 2014 (Phase I): Construction begins on the elevator tower in the Science Building—COMPLETED
  • January 2014: Construction begins in Academic Support Center and Computing Wing—COMPLETED
  • August 2013: Construction begins to distribute the open computing stations—COMPLETED
  • August 2013: Construction begins at the Social Sciences Building and Fairlane Center North—COMPLETED