Science Building renovations

Science Building renderingIn June 2012, Michigan Gov. Rick Snyder approved a $30 million capital outlay that will help UM-Dearborn fund its Science Building renovation project. Keep up to date with the progress of the project.

First phase of Science Building renovations completed (April 6, 2015)
Regents approve schematic designs for Science Building renovations (April 19, 2013)
University receives $30 million capital outlay to renovate Science Building (July 16, 2012)

Construction timeline:

  • Spring 2015 (Phase II): Renovations and additions begin in the Science Building; Renovations and additions complete by Fall 2016
  • Spring 2014 (Phase I): Construction begins on the elevator tower in the Science Building—COMPLETED
  • January 2014: Construction begins in Academic Support Center and Computing Wing—COMPLETED
  • August 2013: Construction begins to distribute the open computing stations—COMPLETED
  • August 2013: Construction begins at the Social Sciences Building and Fairlane Center North—COMPLETED